Here's a sample of the meeting schedule. These are just the basics - there are usually a few more each week.
Normal meetings:
Monday - Regular Project Update Teleconference (usually <1 hr)
Wednesday - Design Verification and Transfer Web Meeting (2+ hours)
Thursday - Progress Meeting with Marinette Marine (< 1 hour)
Thursday - Progress Teleconference with Wartsila (Thruster Manufacturer) usually < 1 hr
This week we added two DV&T teleconferences on Friday, and a Master Schedule meeting on Friday.
Add in a number of teleconferences during the week (at least one per day), and you have a pretty busy week. In addition, we have a bunch of "passageway conferences" in the office.
In spite of all the meetings, we are getting a lot of work done. Typically, all of us are in the office by 7:30 (usually earlier), and leave between 4:30 and 5:30 depending on what's happening. Not *all* of the time is spent drinking coffee and telling sea stories ;) It's a happy crew.
Currently, we are at about 1/2 of our expected office staff. On site are:
Gary: Shipyard Project Director (The Big Kahuna)
John: Shipyard Contract Manager (The Big Organizer)Yours Truly: Marine Science Technical Director (The Big -click here-)
- soon to be joined by -
TBA: Office Assistant
- to be joined in the fall by -
TBA: Inspectors (2)